top of page

Babson College

  • Asphalt walkways, approx. 250’

  • Removed existing asphalt, removed existing gravel

  • Realigned walkway paths

  • Installed new gravel

  • Installed new asphalt, approx. 50 tons

  • Removed existing granite steps

  • Removed all compromised concrete base

  • Repaired concrete base

  • Installed existing granite steps with new steel pins, approx. 36’ wide

  • Fabricated and installed new steel handrail                                                                 

  • Removed existing asphalt curbing

  • Prepped area to receive new granite curbing

  • Installed new granite curbing, approx. 200’

  • Rebuild existing drain manhole with new frame and cover

IMG_2837.JPG

New Asphalt Walkways

TimePhoto_20240628_111817.jpg

New Granite Steps

IMG_2838.JPG

New Granite Curbing